Multi-Million Dollar Manufacturer of Metal Fabricated Engine Gaskets and Components |
|
- Company announced that they were closing their doors
- Capacity issues existed with several product lines past due
- 50% of the hourly workforce was inexperienced
- Needed to move over 170 tools to Japan
- Inventory Bank plan is not feasible
- Language and cultural issues exists when interacting with upper management
|
|
- Become a part of the management team
- Establish regular meetings management to discuss daily progress and priorities
- Monitor manufacturing activities on all shifts
- Develop an inventory bank tracking mechanism
- Provide solutions to the company's team to increase capacity
- Maximize equipment utilization
- Analyze the Inventory Bank plan to ensure feasibility
|
|
- Completed the bank plan in the specified time frame
- Improved output previously past due product lines
- Efforts eliminated further missed jobs for our clients
|
|